• Home
  • Portfolio
  • Services
    • Planning and Scheduling
    • BIM Modeling
    • Quantity Estimation
    • Learning Center
    • Additional Services
  • About us
  • Contact Us
  • CAREERS
  • More
    • Home
    • Portfolio
    • Services
      • Planning and Scheduling
      • BIM Modeling
      • Quantity Estimation
      • Learning Center
      • Additional Services
    • About us
    • Contact Us
    • CAREERS
  • Home
  • Portfolio
  • Services
    • Planning and Scheduling
    • BIM Modeling
    • Quantity Estimation
    • Learning Center
    • Additional Services
  • About us
  • Contact Us
  • CAREERS

Sarasota County - Dona Bay Surface Water Storage Facility – Phase 2

1/2

Project description: 

The project includes modifications to the existing lake berm and embankment to create 364 acres of storage area, emergency lake overflow, installation of 8,100 feet of 72-inch diameter pipe to convey stormwater from Salt Creek rehydration area into the new storage lake and accommodate the surrounding properties off-site drainage flows. The project includes earthwork, pond excavation, installation of drainage structures, large-diameter reinforced concrete pipe, lake berm grading, and aquatic plantings.


Location:  Florida, USA

Main contractor: COBB Site Development INC

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:

  • Review the construction performance.
  • Prepare the monthly updates.
  • Propose recovery options to maintain the schedule and avoid any delays.

Hungry Horse Sump Pump Replacement

Project description: 

The Improvements under this Contract consist of replacing the old existing sump pumps alongside with portion of the sump pump floor grating, all panel boxes, automatic grease pump assembly, the existing base plate, the existing 2 motors, the pipes with the pipe hangers and anchors with a new system. The new system contains locate and install new controls, new base assembly for sump pump pipe support, new mobile A-frame crane with chain hoist and new support structure and grating to accommodate new piping system and crane access.


Location: 

Owner: Bureau of Reclamation

Main contractor: ASG, LLC

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:

  •  Review the construction performance.
  • prepare the monthly updates. 
  • propose recovery options to maintain the schedule and avoid any delays.

SOUTH CANAL IMPROVEMENTS – PHASE 2

Project description: 

The Work is located on the Highlands Reservoir, Highlands EOC, SJRA South Canal Bypass, and SJRA South Canal in east Harris County, TX.

R&T Ellis Excavating, Inc are responsible for: 

-The replacement of two siphons, levee improvements, installation of an access culvert in the SJRA South Canal Bypass, and installation of an all-weather access roadway on the Highlands Reservoir Dam.


Location:  TEXAS, USA


Owner: SAN JACINTO RIVER AUTHORITY

Main contractor: R&T ELLIS EXCAVATING, INC 

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:

  • Review the project documents.
  • Prepare the Baseline schedule to include the scope of with the suitable plan to fit the available resources and to meet the project deadline.

Tampa Bay Water Eldridge-Wilde Will field and Cypress Trails Improvements.

1/2

Project description: 

This project is designed to optimize operations of the wellfield and enhance wellfield reliability, energy efficiency, and safety. It includes the replacement of the pumps, motors, and enclosures at 24 wells. The other 10 wells will remain in place, but not in service, for potential future use.


Project budget: $13.3 million .

Location:  TAMPA BAY.


Main contractor: Randall Construction

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:.

  • Study the project status, 
  • Review all the delay events and change orders.
  • Prepare a Claim using the Time impact analysis (TIA) method asking for the extension of Time.



8142 - YARD PIPING IMPROVEMENTS - PHASE 1 PROJECT

Project description: 

The project consists of rehabilitating two buried primary effluent process pipes: a 78-inch Buried Reinforced Concrete Pipe (RCP) and a 96-inch buried RCP. Rehabilitation of the 78-inch line consists of installation of a Cured-in-Place Pipe (CIPP) liner for approximately 490 feet from the West Primaries Effluent Structure to the North Settled Sewage (SES) Vault. Rehabilitation of the 96-inch line consists of the installation of a CIPP liner for approximately 136 feet from the North SES Vault to the Primary Effluent Junction Box (PEJB), and 10 feet of structural concrete crown repair.


Location: San José-Santa Clara Regional Wastewater Facility (FACILITY), 700 Los Esteros Road, San José, Santa Clara County.


Owner: City of San Jose

Main contractor: Michel's.

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:.

  • Review the construction performance. 
  • Prepare the monthly updates.
  • Propose recovery options to maintain the schedule and avoid any delays.

Walsh Harbour - Fast Response Cutters - FRC HOMEPORTING

Project description: 

This project will provide new waterfront and shore facilities required to moor and maintain 6 FRCs and the associated Maintenance Augmentation Team (MAT). The work includes, but is not limited to: demolishing existing Pier 2 and Wharf 2, constructing waterfront structures (new Pier 2, new Wharf 2, three (3) new floating docks), modernizing spaces in existing buildings, site and ground work and all associated utilities. 


Location: United States Coast Guard (USCG) Base Boston, Massachusetts


Owner: United States Coast Guard

Main contractor: Walsh Group 

Organization: HSE Contractor INC.

Position: Planning and CPM scheduling Consultant.

Roles and Responsibilities:.

  • Review the construction performance.
  • prepare the monthly updates.
  • propose recovery options to maintain the schedule and avoid any delays.

Copyright © 2024 Home & Business - All Rights Reserved.

USA, Philadelphia : (C) +17327048442 

Egypt, Cairo : (C) +201024652149


  • Privacy Policy
  • Terms and Conditions

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept